# What should I check before leaving the installation site?
|
|||
|
|
|
||
|
|
Before leaving the site, perform at least the following commissioning checks:
|
||
|
|
• Communication: verify that the station is accessible through either 4G or Ethernet,
|
||
|
|
according to the intended installation configuration.
|
||
|
|
• Power supply: verify that the external power supply is operating correctly, whether mains
|
||
|
|
or solar.
|
||
|
|
• Battery: verify that the internal battery is connected and charging.
|
||
|
|
• Charging indication: check the charging / power LED.
|
||
|
|
• Camera access: verify access to the camera web interface.
|
||
|
|
• Image: check image quality, focus, exposure, and field of view.
|
||
|
|
• Targets: verify that all required targets or prisms are clearly visible in the image.
|
||
|
|
• References: verify that all selected reference targets are clearly visible.
|
||
|
|
• Target identification: verify that the configured processing areas correspond to the
|
||
|
|
intended physical targets.
|
||
|
|
• Distances: verify that the distances from the camera to the monitored targets are known
|
||
|
|
and correctly entered where required for displacement conversion.
|
||
|
|
• Reference configuration: verify that a sufficient and appropriate set of reference targets
|
||
|
|
has been configured.
|
||
|
|
• Reference fit: verify that the reference-network fit and sigma0 are reasonable.
|
||
|
|
• Acquisition: trigger at least one measurement and confirm that valid measurements are
|
||
|
|
produced.
|
||
|
|
• Schedule: verify that the required periodic acquisition schedule is enabled.
|
||
|
|
• Data transfer: verify that data reach the intended server, FTP destination, optional AIMsight
|
||
|
|
Cloud platform, or API consumer.
|
||
|
|
• Timestamps: verify that exported data contain the required timestamp information and that
|
||
|
|
the timezone is understood.
|
||
|
|
• Alarms: where alarms are required, verify their configuration and perform a functional test
|
||
|
|
whenever practical.
|
||
|
|
Whenever possible, allow at least one complete scheduled measurement and data-transfer cycle
|
||
|
|
to run before leaving the site.
|
||
|
|
|
||
|
|
Source : AIMsight FAQ, rév. 1.5
|