Files
aimsight-libredesk/snippets/textes/what-should-i-check-before-leaving-the-installation-site.md
T
maximeandClaude Opus 5.5 10ed887417 Noms plus clairs : snippets/, scripts de test numérotés, verifier_ollama.py
- base_connaissances/ → snippets/ (corpus/ → textes/, instructions.md → consignes_redaction.md, decoupage.py → fichiers.py, importer.py → envoyer.py) ; python3 -m snippets.envoyer.
- instance-de-test/ : 1_demarrer.sh, 2_creer_boite_et_cle.py, 3_brancher_ia.py, 4_essayer_brouillons.py, voir_empreintes.sh, connexion_admin.py.
- ollama/verifier.py → ollama/verifier_ollama.py ; tests, tâches VS Code et docs alignés.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-11-12 10:27:06 +01:00

34 lines
2.0 KiB
Markdown

# What should I check before leaving the installation site?
Before leaving the site, perform at least the following commissioning checks:
• Communication: verify that the station is accessible through either 4G or Ethernet,
according to the intended installation configuration.
• Power supply: verify that the external power supply is operating correctly, whether mains
or solar.
• Battery: verify that the internal battery is connected and charging.
• Charging indication: check the charging / power LED.
• Camera access: verify access to the camera web interface.
• Image: check image quality, focus, exposure, and field of view.
• Targets: verify that all required targets or prisms are clearly visible in the image.
• References: verify that all selected reference targets are clearly visible.
• Target identification: verify that the configured processing areas correspond to the
intended physical targets.
• Distances: verify that the distances from the camera to the monitored targets are known
and correctly entered where required for displacement conversion.
• Reference configuration: verify that a sufficient and appropriate set of reference targets
has been configured.
• Reference fit: verify that the reference-network fit and sigma0 are reasonable.
• Acquisition: trigger at least one measurement and confirm that valid measurements are
produced.
• Schedule: verify that the required periodic acquisition schedule is enabled.
• Data transfer: verify that data reach the intended server, FTP destination, optional AIMsight
Cloud platform, or API consumer.
• Timestamps: verify that exported data contain the required timestamp information and that
the timezone is understood.
• Alarms: where alarms are required, verify their configuration and perform a functional test
whenever practical.
Whenever possible, allow at least one complete scheduled measurement and data-transfer cycle
to run before leaving the site.
Source : AIMsight FAQ, rév. 1.5